Solution of Johnson's Rule

Solution of Johnson's Rule

Home Up

 

Help

 

 

Back to Johnson's Rule Example

Table of Content

Forward to Johnson's Rule Simulation


Solution of example by using the Johnson's Rule rules:

   Given table:

Job Work Centre 1
(Drill)
Work Centre 2
(Lathe)
A 5 2
B 3 6
C 8 4
D 10 7
E 7 12

Set the sequence that will minimise the total processing time for the five jobs:
Step 1    :    The job with the shortest processing time is A, in work centre 2(with a
                    time of 2 hours).
                    Because it is at the second centre, schedule A last.

        A

        Step 2     :    Job B has the next shortest time(3).
                              Because that time is the first work centre, we should schedule it first and
                              eliminate it from the consideration.

B       A

        Step 3     :    The next shortest time is Job C(4) on the second machine.
                               Therefore, place it at last.

B     C A

          Step 4    :     There is a tie(at 7) for the shortest remaining job.
                               We can place E, which was on the first work centre, first.
                               Then D is placed in the last sequencing position.

B E D C A

        The sequencial times are:

Job B E D C A
Work Centre 1 3 7 10 8 5
Work Centre 2 6 12 7 4 2


Figure9     The Time-phased flow of this job sequence is illustrated graphically as below :

jr.jpg (14973 bytes)

 

Simulation by using Johnson's Rule  Simulation on Johnson's Rule

Back to top    Back to Top

[Job Sequencing]    [Johnson's Rule]    [Example with Solution]            [Johnson's Rule Simulation]